Chapter 5 · Install the Link

Power the Link

Connect the power

  1. Ensure the Link is properly mounted.

  2. Connect the provided PSU to an AC socket.

Check

Once the Link is powered, the blue LED next to the power jack will turn on.

Electrical safety

Warning

Loss of electrical safety

Incorrect use may impair device safety. Carefully follow the instructions in this user manual during installation, commissioning, and operation.

Warning

Loss of electrical safety when using an unsuitable power supply

Using an unsuitable power supply can compromise both the device and user safety. Ensure safe operation:

  • The Link is designed exclusively for operation with the supplied power supply (Mean Well NGE30E24-P1J).
  • Do not pull the cable of the power supply over sharp edges or clamp it.
  • Keep the power supply and its cable away from heat and moisture.
  • Do not use the power supply if it or its cable is damaged.

A damaged power supply is not repaired but replaced. Contact info@integer.energy for a replacement.

Warning

Loss of electrical safety when disassembling the product. Dangerous shock currents.

Do not disassemble the device. Doing so may result in electric shock or malfunction.